Decision Maker: Executive Cabinet
Decision status: Recommendations Approved
Is Key decision?: No
Is subject to call in?: Yes
1. Approval to utilise part of the approved Leisure Centre Improvements budget to enable essential structural repair works to be carried out to Brinscall Swimming Pool, work to include repairing structural floors and tank walls. This option would require the closure of the pool for approximately 6 months.
2. Approval to undertake a competitive tender for urgent refurbishment works to Brinscall Pool through the open Chest portal in accordance with procurement procedures.
3. Approval to delegate authority to the Executive Member (Resource) to award the contract to undertake refurbishment works following completion of tender process.
Report author: David Taylor
Publication date: 15/07/2022
Date of decision: 14/07/2022
Decided at meeting: 14/07/2022 - Executive Cabinet
Effective from: 23/07/2022