Decision:

1.    To approve the contract award to mechanical and electrical engineers to complete a design up to RIBA Stage 3 in support of a planning application submission and preparation of tender documents to procure a design & build contractor.

 

2.    To approve the contract award to structural engineers to complete a design up to RIBA Stage 3 in support of a planning application submission and preparation of tender documents to procure a design & build contractor.

Publication date: 17/06/2020

Date of decision: 17/06/2020

Effective from: 25/06/2020