Decision Maker: Executive Member (Resources)
Decision status: Recommendations Approved
Is Key decision?: Yes
Is subject to call in?: Yes
1. To approve the appointment of a contractor to deliver the Alker Lane development.
2. To approve the appointment of a contractor under a JCT (2016) Design and Build contract.
3. To acknowledge that a budget increase is required and that no commitment that exceeds the budget will be made to the appointed contractor until the budget increase has been approved by Council members.
Publication date: 15/03/2021
Date of decision: 15/03/2021
Effective from: 23/03/2021