Decision Maker: Executive Member (Economic Development and Public Service Reform)
Decision status: Recommendations Approved
Is Key decision?: No
Is subject to call in?: Yes
1. To approve the work package for the Clifford Street crossing, as shown in Appendix A, as part of the Market Walk Extension scheme.
2. To approve the expenditure of up to £162,723 for the delivery of the above works package.
3. To delegate authority to the Director for Business Development & Growth to authorise any subsequent variations, arising during the works, which can be contained within the remaining scheme budget (£16,364,643) approved in the January report.
Publication date: 09/08/2018
Date of decision: 09/08/2018
Effective from: 17/08/2018
Accompanying Documents: