Recommendations approved
Reasons for recommendations
To continue with the improvements to Chorley Bus Station
The proposals and funding have already been approved at Cabinet, however the procurement strategy needs to be approved for the project to proceed.
Other options considered and rejected
Take the report to Cabinet before EMD. This was rejected as there is no Cabinet until September, the project is part funded via the UKSPF program. All projects funded by this program need to be finished before April 2025.