King George V Playing Fields Pavilion Contract Budget
The current budget established for the King
George V Pavilion scheme, as stated in the Capital Monitoring
Report approved by Executive Cabinet in February 2022, is
£908,000 comprising £674,953 in s106 and £233,570
in CIL.
Following receipt of tenders the value of the work is
£939,000 and approval is therefore requested for an increase
in the scheme budget of £31,000 which can be funded from the
£50,000 King George V Playing Fields CIL (play) contribution
already allocated to the King George V project.
CIL Officers advise that for the purposes of the Infrastructure
Funding Statement (IFS)
Decision type: Non-key
Decision status: Recommendations Approved
Notice of proposed decision first published: 09/05/2022
Decision due: 29 Apr 2022 by Director (Planning and Development)
Contact: Simon Forster, Open Space Strategy Officer Email: simon.forster@chorley.gov.uk Email: simon.forster@chorley.gov.uk.