Decision Maker: Executive Cabinet
Decision status: Recommendations Approved
Is Key decision?: Yes
Is subject to call in?: Yes
To authorise the appointment of Speakman Contractors to undertake work to modernise and refurbish Astley Farmhouse and create an exhibition space as detailed in the report.
The Executive Member for People presented the confidential report which sought approval to appointment Speakman Contractors to undertake work to modernise and refurbish Astley Farmhouse and create an exhibition space.
During the detailed design and specification stage additional work was identified to bring the building up to modern standards and meet current building legislation. This included mechanical and engineering work to fit a steel frame internally to provide structural stability and new electrics, lighting and heating systems.
Decision made
Authorisation granted to the appointment of Speakman Contractors to undertake work to modernise and refurbish Astley Farmhouse and create an exhibition space as detailed in the report.
Reason(s) for decision
To create a new exhibition space and to bring the whole farmhouse building up to a modern standards. It is more cost effective to undertake all of the work together and it would also ensure the building was ready to be utilised for other potential purposes in the future.
Alternative option(s) considered and rejected
None.
Publication date: 13/12/2013
Date of decision: 12/12/2013
Decided at meeting: 12/12/2013 - Executive Cabinet
Effective from: 01/01/2014