Decision Maker: Executive Cabinet
Decision status: Recommendations Approved
Is Key decision?: Yes
Is subject to call in?: Yes
1. To approve the proposed procurement methodologies and evaluation criteria for the building contract comprising a single stage open tender with suitability questionnaire / 100% quality evaluation and the use of the JCT design and build form of building contract.
2. To approve the omission of the social value element of evaluation.
3. To approve the delegation of the contract award to Executive Member Decision.
Report author: Simon Forster
Publication date: 20/06/2022
Date of decision: 16/06/2022
Decided at meeting: 16/06/2022 - Executive Cabinet
Effective from: 28/06/2022