Agenda item

A4:08/01079/OUTMAJ - Radburn Works, Sandy Lane, Clayton-Le-Woods

Report of Corporate Director (Business) (enclosed)

Decision:

Permission granted subject to a legal agreement

Minutes:

(The Committee received representations from the applicant’s agents in support of the proposals)

 

Application no:            08/01079/OUTMAJ

Proposal:                   Outline application for residential redevelopment incorporating ancillary open space, landscaping and associated infrastructure.

Location:                    Radburn Works, Sandy Lane, Clayton-Le-Woods, Chorley

Decision:

It was proposed by Councillor Harold Heaton, seconded by Councillor Mick Muncaster, and was subsequently RESOLVED to grant planning permission subject the signing of the Legal Agreement by 13 January 2009 and the following conditions and that if the Legal Agreement was not signed by this date, then planning permission would be refused.

 

1. An application for approval of the reserved matters (namely siting, scale, external appearance of the buildings and landscaping of the site) must be made to the Council before the expiration of three years from the date of this permission and the development hereby permitted must be begun two years from the date of approval of the last of the reserved matters to be approved.

Reason: Required to be imposed by Section 92 of the Town and Country Planning Act 1990 as amended by Section 51 of the Planning and Compulsory Purchase Act 2004.

 

2. Before the development hereby permitted is first commenced, full details of the position, height and appearance of all fences and walls to be erected (notwithstanding any such detail shown on previously submitted plans) shall have been submitted to and approved in writing by the Local Planning Authority.  No dwelling shall be occupied until all fences and walls shown in the approved details to bound its plot have been erected in conformity with the approved details.  Other fences and walls shown in the approved details shall have been erected in conformity with the approved details prior to substantial completion of the development.

Reason:  To ensure a visually satisfactory form of development, to provide reasonable standards of privacy to residentsand in accordance with Policy No. HS4 of the Adopted Chorley Borough Local Plan Review.

 

3. The application for approval of reserved matters shall be accompanied by full details of existing and proposed ground levels and proposed building slab levels (all relative to ground levels adjoining the site), notwithstanding any such detail shown on previously submitted plans.  The development shall only be carried out in conformity with the approved details.

Reason: To protect the appearance of the locality, in the interests of the amenities of local residents and in accordance with Policy Nos. GN5 and HS4 of the Adopted Chorley Borough Local Plan Review.

 

4. No development shall take place until a scheme of landscaping has been submitted to and approved in writing by the Local Planning Authority, notwithstanding any such detail which may have previously been submitted.  The scheme shall indicate all existing trees and hedgerows on the land; detail any to be retained, together with measures for their protection in the course of development; indicate the types and numbers of trees and shrubs to be planted, their distribution on site, those areas to be seeded, paved or hard landscaped; and detail any changes of ground level or landform. The details shall also demonstrate that the biodiversity resource within the application area will be enhanced as part of the proposals. The scheme should include a landscaping/habitat creation and management plan which should aim to contribute to targets specified in the UK and Lancashire Biodiversity Action Plans. Landscaping proposals should comprise only native plant communities appropriate to the natural area.

Reason: In the interests of the amenity of the area and in accordance with Government advice contained in PPS9, Policy EM1 of the North West Regional Spatial Strategy and  Policies No.GN5 and EP9  of the Adopted Chorley Borough Local Plan Review.

 

5. All planting, seeding or turfing comprised in the approved details of landscaping shall be carried out in the first planting and seeding seasons following the occupation of any buildings or the completion of the development, whichever is the sooner, and any trees or plants which within a period of 5 years from the completion of the development die, are removed or become seriously damaged or diseased shall be replaced in the next planting season with others of similar size and species, unless the Local Planning Authority gives written consent to any variation.

Reason:  In the interest of the appearance of the locality and in accordance with Policy No GN5 of the Adopted Chorley Borough Local Plan Review.

 

6. During the construction period, all trees to be retained shall be protected by 1.2 metre high fencing as specified in paragraph 8.2.2 of British Standard BS5837:2005 at a distance from the tree trunk equivalent to the outermost limit of the branch spread, or at a distance from the tree trunk equal to half the height of the tree (whichever is further from the tree trunk), or as may be first agreed in writing with the Local Planning Authority.   No construction materials, spoil, rubbish, vehicles or equipment shall be stored or tipped within the areas so fenced.  All excavations within the area so fenced shall be carried out by hand.

Reason: To safeguard the trees to be retained and in accordance with Policy Nos. EP9 of the Adopted Chorley Borough Local Plan Review.

 

7. The development hereby permitted shall not commence until samples of all external facing materials to the proposed buildings (notwithstanding any details shown on previously submitted plans and specification) have been submitted to and approved in writing by the Local Planning Authority.  The development shall only be carried out using the approved external facing materials.

Reason:  To ensure that the materials used are visually appropriate to the locality and in accordance with Policy Nos. GN5 and HS4 of the Adopted Chorley Borough Local Plan Review.

 

8. The development hereby permitted shall not commence until full details of the colour, form and texture of all hard ground- surfacing materials (notwithstanding any such detail shown on previously submitted plans and specification) have been submitted to and approved in writing by the Local Planning Authority.  The development shall only be carried out in conformity with the approved details.

Reason:  To ensure a satisfactory form of development in the interest of the visual amenity of the area and in accordance with Policy Nos. GN5 and HS4 of the Adopted Chorley Borough Local Plan Review.

 

9. The application for approval of Reserved Matters shall be accompanied by full details of the predicted energy use of the development expressed in terms of carbon emissions and a schedule setting out how energy efficiency is being addressed, including benchmark data.  It will show the on-site measures to be installed and implemented so as to produce a minimum of 10%, or locally set targets (whichever is the higher) in place at the receipt of the reserved matters, of the predicted energy use of the development by means of low carbon energy sources. Appropriate on-site measures include rainwater/brown water recycling, the implementation of sustainable urban drainage systems and the provision of storage space for recyclable waste materials and composting.  No development shall commence until the scheme has been submitted to and approved in writing by the Local Planning Authority. Such details as may be approved shall be implemented and retained in perpetuity unless otherwise agreed in writing by the Local Planning Authority.

Reason: To ensure the proper planning of the area. In line with the objective of National Planning Policy contained in Planning Policy Statement: Planning, the Climate Change Supplement to PPS1, Policies EM16 and EM17 of the Regional Spatial Strategy and Chorley Borough Council’s Sustainable Resources DPD.

 

10. The application for approval of Reserved Matters shall demonstrate and provide full details of how the design and layout of the buildings will withstand climate change. The scheme shall include details of the Code for Sustainable Homes Level, how the proposals minimise energy use and maximise energy efficiency. All dwellings commenced after 2010 will be required to meet Level 3, all dwellings commenced after 2013 will be required to meet Level 4 and all dwellings commenced after 2016 will be required to meet Level 6 of the Codes for Sustainable Homes. No development shall commence until the scheme has been submitted to and approved in writing by the Local Planning Authority. Such details as may be approved shall be implemented and retained in perpetuity unless otherwise agreed in writing by the Local Planning Authority.

Reason: To ensure the proper planning of the area. In line with the objective of National Planning Policy contained in Planning Policy Statement: Planning, the Climate Change Supplement to PPS1, Policies EM16 and EM17 of the Regional Spatial Strategy and Chorley Borough Council’s Sustainable Resources DPD.

 

11. No dwelling hereby permitted shall be occupied until the highway alterations to the site access with Sandy Lane have been completed in accordance with the details shown on plan reference Figure 3.1, or as otherwise agreed in writing by the Local Planning Authority.

Reason:  In the interests of highway safety and in accordance with Policy No.TR4 of the Adopted Chorley Borough Local Plan Review.

 

12. No dwelling hereby permitted shall be occupied until that part of the service road which provides access to it from the public highway has been constructed in accordance with plans which have been submitted to and approved in writing by the Local Planning Authority.

Reason:  In the interests of highway safety and in accordance with Policy No.TR4 of the Adopted Chorley Borough Local Plan Review.

 

13. The outline planning permission hereby approved relates to the erection of upto 100 residential units. The application for reserved matters shall not exceed 100 residential units.

Reason: In the interests of the appropriate development of the site, to prevent intensification in the development of the site and in the interests of the visual amenities of the area. In accordance with Government advice contained in PPS3: Housing and Policy HS4 of the Adopted Chorley Borough Local Plan Review

 

14. Prior to the commencement of the development a strategy to attenuate surface water discharges shall be submitted to and approved in writing by the Local Planning Authority. The Strategy should demonstrate that existing Greenfield rates will be achieved. The surface water drainage scheme shall thereafter be completed in accordance with the approved strategy.

Reason: To reduce the risk of flooding at the site and in accordance with Government advice contained in PPS25: Development and Flood Rick.

 

15. Surface water must drain separate from the foul and no surface water will be permitted to discharge to the foul sewerage system.

Reason: To secure proper drainage and in accordance with Policy Nos. EP17 of the Adopted Chorley Borough Local Plan Review.

 

16. The pedestrian and cycle improvements to Sandy Lane and Radburn Bridge specified in the drawings reference Figure 3.1 and Figure 3.2 received 14th October 2008, unless otherwise agreed in writing by the Local Planning Authority, shall be constructed and completed prior to the occupation of the dwellinghouses hereby permitted.

Reason: In the interest of highway safety and in accordance with Policy TR4 of the Adopted Chorley Borough Local Plan Review.

17. Prior to the commencement of the development hereby permitted the further investigation works and any proposed remediation shall be carried out in accordance with the recommendations set out in the submitted Geo-Environmental Assessment Report prepared by Brownfield Solutions Ltd (reference AJH/C1307/865) and in accordance with a suitable remediation strategy. The further works shall include a complete gas monitoring programme to adequately characterise risks to the proposed end users from ground gases; installation of suitable gas protection measures (where required); investigation of the extent of hydrocarbons and of peat to identify removal or treatment as required; where the remedial strategy dictates import clean cover into garden and landscaping areas (600mm and 450mm respectively) and validation of cover system. The further works and suggested remedial measures recommended in Section 9 and 10 of the submitted report.

Reason: To protect the environment and prevent harm to human health by ensuring that the land is remediated to an appropriate standard for the proposed end use and in accordance with Government advice contained in PPS23: Planning and Pollution Control

 

18. Upon completion of the remediation works a validation report containing any validation sampling results shall be submitted to and approved in writing by the Local Planning Authority.

Reason: To protect the environment and prevent harm to human health by ensuring that the land is remediated to an appropriate standard for the proposed end use and in accordance with Government advice contained in PPS23: Planning and Pollution Control

 

19. If, during development, contamination not previously identified is found to be present at the site then no further development (unless otherwise agreed in writing with the Local Planning Authority) shall be carried out on the area of land affected until the developer has submitted, and obtained written approval from the Local Planning Authority for, an amendment to the Method Statement detailing how this unsuspected contamination shall be dealt with.

Reason: To protect the environment and prevent harm to human health by ensuring that the land is remediated to an appropriate standard for the proposed end use and in accordance with Government advice contained in PPS23: Planning and Pollution Control

 

20. No development shall take place until a programme of archaeological work has been implemented in accordance with a scheme of investigation which has previously been submitted to and approved in writing by the Local Planning Authority.

Reason:  The site is situated within an area of known archaeological interest and, as such, the site should be appropriately excavated and the remains recorded and in accordance with Policy Nos. HT11 and HT12 of the Adopted Chorley Borough Local Plan Review.

 

21. Prior to the commencement of the development hereby permitted the vehicular access link through the car park of the Lord Nelson Public House shall cease to be used. Full details of the measures to be implemented to prevent vehicular access shall be submitted to and approved in writing by the Local Planning Authority. The details shall include details of the proposed pedestrian/ cycle link. The development thereafter shall be carried out in accordance with the approved scheme.

Reason: To ensure the acceptable development of the site and in accordance with Policy GN5 of the Adopted Chorley Borough Local Plan Review.