Agenda item

09/00985/OUTMAJ - Chorley Motor Auction, Cottam Street, Chorley PR7 2DT

Report of Director of Partnerships, Planning and Policy (enclosed).

Decision:

Approve outline planning permission, subject to the completion of a Section 106 Legal Agreement and recommended conditions (including an additional condition to regulate demolition and construction hours of working).

Minutes:

Application No:                      09/00985/OUTMAJ

Proposed:                              Application for outline planning permission for the erection of 15 affordable dwellings, following the demolition of the existing commercial premises.

Location:                                Chorley Motor Auction, Cottam Street, Chorley

 

Decision:

 

It was proposed by Councillor Kenneth Ball, seconded by Councillor Ralph Snape, and subsequently RESOLVED that outline planning approval be granted, subject to the following conditions and the prior completion of an associated Section 106 Legal Agreement:

 

1. An application for approval of the reserved matters (namely scale, external appearance of the buildings and landscaping of the site) must be made to the Council before the expiration of three years from the date of this permission and the development hereby permitted must be begun two years from the date of approval of the last of the reserved matters to be approved.

Reason: Required to be imposed by Section 92 of the Town and Country Planning Act 1990 as amended by Section 51 of the Planning and Compulsory Purchase Act 2004.

 

2. The approved plans are:

Plan Ref.                            Received On:                      Title:

09/120/P01                         8th December 2009            Location Plan

09/120/P01 Rev B            30th March 2010                 Proposed Site Plan

                                             15th February 2010            Topographical Survey

Reason: To define the permission and in the interests of the proper development of the site.

 

3. The application for approval of reserved matters shall be accompanied by full details of existing and proposed ground levels and proposed building slab levels (all relative to ground levels adjoining the site), notwithstanding any such detail shown on previously submitted plans. The development shall only be carried out in conformity with the approved details.

Reason: To protect the appearance of the locality, in the interests of the amenities of local residents and in accordance with Policy Nos. GN5 and HS4 of the Adopted Chorley Borough Local Plan Review.

 

4. Before the development hereby permitted is first commenced, full details of the position, height and appearance of all fences and walls to be erected (notwithstanding any such detail shown on previously submitted plans) shall have been submitted to and approved in writing by the Local Planning Authority. No dwelling shall be occupied until all fences and walls shown in the approved details to bound its plot have been erected in conformity with the approved details. Other fences and walls shown in the approved details shall have been erected in conformity with the approved details prior to substantial completion of the development.

Reason: To ensure a visually satisfactory form of development, to provide reasonable standards of privacy to residents and in accordance with Policy No. HS4 of the Adopted Chorley Borough Local Plan Review.

 

5. Surface water must drain separate from the foul and no surface water will be permitted to discharge to the foul sewerage system.

Reason: To secure proper drainage and in accordance with Policy Nos. EP17 of the Adopted Chorley Borough Local Plan Review.

 

6. No development shall take place until a scheme of landscaping has been submitted to and approved in writing by the Local Planning Authority, notwithstanding any such detail which may have previously been submitted. The scheme shall indicate all existing trees and hedgerows on the land; detail any to be retained, together with measures for their protection in the course of development; indicate the types and numbers of trees and shrubs to be planted, their distribution on site, those areas to be seeded, paved or hard landscaped; and detail any changes of ground level or landform.

Reason: In the interests of the amenity of the area and in accordance with Policy No.GN5 of the Adopted Chorley Borough Local Plan Review.

 

7. All planting, seeding or turfing comprised in the approved details of landscaping shall be carried out in the first planting and seeding seasons following the occupation of any buildings or the completion of the development, whichever is the sooner, and any trees or plants which within a period of 5 years from the completion of the development die, are removed or become seriously damaged or diseased shall be replaced in the next planting season with others of similar size and species, unless the Local Planning Authority gives written consent to any variation.

Reason: In the interest of the appearance of the locality and in accordance with Policy No GN5 of the Adopted Chorley Borough Local Plan Review.

 

8. The development hereby permitted shall not commence until samples of all external facing materials to the proposed buildings (notwithstanding any details shown on previously submitted plans and specification) have been submitted to and approved in writing by the Local Planning Authority. The development shall only be carried out using the approved external facing materials.

Reason: To ensure that the materials used are visually appropriate to the locality and in accordance with Policy Nos. GN5 and HS4 of the Adopted Chorley Borough Local Plan Review.

 

9. The development hereby permitted shall not commence until full details of the colour, form and texture of all hard ground- surfacing materials (notwithstanding any such detail shown on previously submitted plans and specification) have been submitted to and approved in writing by the Local Planning Authority. The development shall only be carried out in conformity with the approved details.

Reason: To ensure a satisfactory form of development in the interest of the visual amenity of the area and in accordance with Policy Nos. GN5 and HS4 of the Adopted Chorley Borough Local Plan Review.

 

10. Notwithstanding the provisions of the Town and Country Planning (General Permitted Development) Order 1995, (Schedule 2, Part 1, Classes A to E), or any Order amending or revoking and re-enacting that Order, no alterations or extensions shall be undertaken to the dwellings hereby permitted, or any garage, shed or other outbuilding erected (other than those expressly authorised by this permission).

Reason: To protect the appearance of the locality and in accordance with Policy No. HS4 of the Adopted Chorley Borough Local Plan Review.

 

11. The development hereby permitted shall be carried out in accordance with the bat mitigation proposals set out within Section 5 of the Bat Survey undertaken by ERAP Consultant Ecologists dated 30th January 2010.

Reason: To ensure the continued protection and enhancement of bats. In accordance with Government advice contained in PPS9 and Policy EP4 of the Adopted Chorley Borough Local Plan Review.

 

12. No development shall take place until details of the proposed surface water drainage arrangements have been submitted to and approved by the Local Planning Authority in writing. No part of the development shall be occupied until the approved surface water drainage arrangements have been fully implemented.

Reason: To secure proper drainage and to prevent flooding and in accordance with Government advice contained in PPS25: Development and Flood Risk.

 

13. Prior to the commencement of the development a report to identify any potential sources of contamination on the site and where appropriate, necessary remediation measures, shall be submitted to and approved in writing by the Local Planning Authority. The report should include an initial desk study, site walkover and risk assessment. If the initial study identifies the potential for contamination to exist on site, the scope of a further study must then be agreed in writing with Local Planning Authority and thereafter undertaken including details of the necessary remediation measures. The development shall thereafter only be carried out following the remediation of the site in full accordance with the measures stipulated in the approved report.

Reason: In the interests of safety and in accordance with Government advice contained in PPS23: Planning and Pollution Control.

 

14. If, during development, contamination not previously identified is found to be present at the site then no further development (unless otherwise agreed in writing with the Local Planning Authority) shall be carried out until the developer has submitted, and obtained written approval from the Local Planning Authority for, an amendment to the Method Statement detailing how this unsuspected contamination shall be dealt with.

Reason: To protect the environment and prevent harm to human health by ensuring that the land is remediated to an appropriate standard for the proposed end use and in accordance with Government advice contained in PPS23: Planning and Pollution Control.

 

15. The application for approval of Reserved Matters shall demonstrate and provide full details of how the design and layout of the buildings will withstand climate change in accordance with the submitted Sustainability Statement prepared by Lawson Margerison Partnership Ltd received 8th December 2009 and the Sustainability Statement Revision A dated 9th March 2010. The approved details shall be fully implemented and retained in perpetuity.

Reason: To ensure the proper planning of the area. In accordance with Government advice contained in Planning Policy Statement: Planning and Climate Change - Supplement to Planning Policy Statement 1 and in accordance with Policies EM16 and EM17 of the North West Regional Spatial Strategy and Policy SR1 of Chorley Borough Council's Adopted Sustainable Resources Development Plan Document and Sustainable Resources Supplementary Planning Document.

 

16. The application for approval of reserved matters shall be accompanied by a Design Stage assessment and related certification demonstrating that the proposed development will be constructed to achieve the relevant Code for Sustainable Homes level. All dwellings commenced after 1st January 2010 will be required to meet Code Level 3, all dwellings commenced after 1st January 2013 will be required to meet Code Level 4 and all dwellings commenced after 1st January 2016 will be required to meet Code Level 6. In accordance with Policy SR1 of the Sustainable Resources DPD, renewable or low carbon energy sources must be installed to reduce the predicted carbon emissions of the development by at least 15% (increasing to 20% from 2015).  To demonstrate that this has been achieved, the Design Stage certification must show that the proposed development will achieve 2 credits within Issue Ene 7: Low or Zero Carbon Technologies. The approved details shall be fully implemented and retained in perpetuity.

Reason: To ensure the proper planning of the area. In accordance with Government advice contained in Planning Policy Statement: Planning and Climate Change - Supplement to Planning Policy Statement 1 and in accordance with Policies EM16 and EM17 of the North West Regional Spatial Strategy and Policy SR1 of Chorley Borough Council's Adopted Sustainable Resources Development Plan Document and Sustainable Resources Supplementary Planning Document.

 

17. No dwelling shall be occupied until a Code for Sustainable Homes ‘Post Construction Stage’ assessment has been carried out and a final Code Certificate has been issued certifying that the required Code Level and 2 credits under Issue Ene7 has been achieved and the certificate has been submitted to and approved in writing by the Local Planning Authority.

Reason: To ensure the proper planning of the area. In accordance with Government advice contained in Planning Policy Statement: Planning and Climate Change - Supplement to Planning Policy Statement 1 and in accordance with Policies EM16 and EM17 of the North West Regional Spatial Strategy and Policy SR1 of Chorley Borough Council's Adopted Sustainable Resources Development Plan Document and Sustainable Resources Supplementary Planning Document.

 

18. The application for approval of reserved matters shall be accompanied by a scheme and programme for the site enabling and construction phase of the development.  The scheme and programme shall cover:

1. Site/construction access points for each phase of development and mechanisms of limiting access from Cottam Street.

2. Site compound and contractor parking and management of contractors parking.

3. Construction operating hours including deliveries and site construction staff.

The approved scheme and programme shall be implemented in accordance with the approved details.

Reason:  to ensure the access used for construction traffic is appropriate in highway safety terms and to ensure that noise and disturbance resulting from hours of operation and delivery does not adversely impact on the amenity of existing residents.

Supporting documents: